2025-26 Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for March 23 to April 3
Below is the anticipated schedule of work from March 23 to April 3, 2026.
Brighton High School
Technology Suite:
- Shop equipment connections and adjustments
- Electrical finishes
Door 20 Addition:
- Countertop and window trim
- Heat pump work
- Ceiling work and lighting in hallway outside addition
Music Suite:
- Electrical rough-in
- Mechanical rough-in
- Framing
- Panel work
- Hanging heat pumps
Athletic Fields and New Entry Lane:
- Subject to material arrival, there will be placement and installation of stone for new entry lane, drop-off loop and temporary laydown area which is next to the Buildings and Grounds lot
- Site prep
Boiler Room/MDP:
- Mechanical and plumbing rough-in
- Cooling tower rough-in: Welding and roof work
- Hot water boiler connections
- Electrical conduit rough-in and panel work and transformer installation
- Plumbing sump pump piping
Twelve Corners Middle School
STEAM Suite:
- Drywall work
- Painting
Stairwells:
- Painting
- Ceiling work
Elevator:
- Electrical card reader programming
- Electrical panel work and testing
French Road Elementary School
Exterior Canopy:
- Roofing drainage work dependent on weather
Main Lobby/Secure Vestibule:
- Metal coiling door electrical connections
- Door hardware
- Painting touch-ups
Council Rock Primary School
Crawlspace:
- Plumbing Lines
Mezzanine:
- Demo and Abatement
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.