2025-26 Construction Schedule

Brighton Construction Schedule

Brighton Construction Schedule for March 23 to April 3

 

Below is the anticipated schedule of work from March 23 to April 3, 2026.

 

Brighton High School

Technology Suite:

  • Shop equipment connections and adjustments
  • Electrical finishes

Door 20 Addition:

  • Countertop and window trim
  • Heat pump work
  • Ceiling work and lighting in hallway outside addition

Music Suite:

  • Electrical rough-in
  • Mechanical rough-in
  • Framing
  • Panel work
  • Hanging heat pumps

Athletic Fields and New Entry Lane:

  • Subject to material arrival, there will be placement and installation of stone for new entry lane, drop-off loop and temporary laydown area which is next to the Buildings and Grounds lot
  • Site prep

Boiler Room/MDP:

  • Mechanical and plumbing rough-in
  • Cooling tower rough-in: Welding and roof work
  • Hot water boiler connections
  • Electrical conduit rough-in and panel work and transformer installation
  • Plumbing sump pump piping

 

Twelve Corners Middle School

STEAM Suite:

  • Drywall work
  • Painting

Stairwells:

  • Painting
  • Ceiling work

Elevator:

  • Electrical card reader programming
  • Electrical panel work and testing

 

French Road Elementary School

Exterior Canopy:

  • Roofing drainage work dependent on weather

Main Lobby/Secure Vestibule:

  • Metal coiling door electrical connections
  • Door hardware
  • Painting touch-ups

 

Council Rock Primary School

Crawlspace:

  • Plumbing Lines

Mezzanine:

  • Demo and Abatement

 

Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.

 

Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.

A construction schedule for 2025-26 lists projects for several schools, including Brighton and Twelve Corners.